HPR1000 passes U.K. design assessment
The Office for Nuclear Regulation (ONR) and the Environment Agency (EA) have found the UK HPR1000 reactor suitable for construction in the United Kingdom, the regulators jointly announced last week.
The Office for Nuclear Regulation (ONR) and the Environment Agency (EA) have found the UK HPR1000 reactor suitable for construction in the United Kingdom, the regulators jointly announced last week.
As part of its drive for carbon neutrality by 2050, France will build at least six new nuclear reactors in the coming decades, according to a February 10 article from Reuters. "What our country needs, and the conditions are there, is the rebirth of France's nuclear industry," French president Emmanuel Macron said as he announced France’s new nuclear strategy.
Macron also said that he wanted to extend the life spans of France’s existing nuclear plants.
The price tag: The six new plants would be built and operated by state-controlled energy provider EDF, which has estimated the cost of those plants total at about 50 billion euros (about $57 billion), depending on financing conditions, according to the article.
The first new reactor, an evolution of the European Pressurized Reactor (EPR), would come on line by 2035, Macron said. The article added that the country would embark on a study to determine whether a further eight reactors beyond the initial six would be needed.
The Department of Energy’s Office Nuclear Energy has launched a $6 billion program aimed at preserving the existing U.S. fleet of nuclear power reactors. Established under the Bipartisan Infrastructure Law, the Civil Nuclear Credit Program will allow owners and operators of commercial nuclear power reactors at economic risk of shutting down to apply for credits via a sealed bid process.
The Tennessee Valley Authority’s board of directors has given the go-ahead for a program that will explore the development and potential deployment of small modular reactors as part of the utility’s decarbonization strategy.
The United Kingdom’s Office for Nuclear Regulation (ONR) has granted permission for the start of bulk mechanical, electrical, and HVAC component installation work at the Hinkley Point C site in Somerset, England, where two 1,630-MWe EPRs are under construction. Thus far, most of the activity at Hinkley Point C has been in the field of civil construction.
This new phase, according to ONR, will require a workforce of up to 4,000 during peak times, including welders, pipe fitters, and electricians. The work is to be accomplished over a three-year period, with NNB Genco—the EDF Energy subsidiary set up in 2009 to build and operate Hinkley Point C—teaming up with four suppliers: Balfour Beatty Bailey, Doosan, Cavendish, and Altrad.
Two GOP lawmakers are calling on the Government Accountability Office to undertake an assessment of the Nuclear Regulatory Commission’s preparedness to review and approve advanced reactor applications.
In a February 4 letter to the GAO, Sen. Shelley Moore Capito (R., W.Va.), ranking member of the Senate Environment and Public Works Committee, and Rep. Cathy McMorris Rodgers (R., Wash.), ranking member of the House Energy and Commerce Committee, wrote, “Recent NRC actions concerning certain licensing activities raise questions about the agency’s capability to manage effectively first-mover applications for new, advanced technologies.”
Small modular reactor developer NuScale Power has informed the Nuclear Regulatory Commission via letter that a combined license application (COLA) for the Carbon Free Power Project’s SMR plant is expected to be submitted to the agency in January 2024. The COLA will be for a six-unit 77-MWe plant.
The public power consortium Utah Associated Municipal Power Systems launched the Carbon Free Power Project in 2015 to develop, own, and operate the nation’s first SMR plant, to be located at Idaho National Laboratory, with reactor technology supplied by NuScale.
Seventy-nine scientific and business luminaries, including a number of the world’s leading experts on climate and energy, have signed a letter imploring California Gov. Gavin Newsom to postpone the premature retirement of the Diablo Canyon nuclear power plant, currently slated for closure in 2025.
The European Commission gave two cheers for nuclear energy yesterday with its adoption of the Complementary Climate Delegated Act (CDA), which adds—under what the EC refers to as “clear and strict conditions”—nuclear and natural gas to the list of green technologies covered by the EU taxonomy. (The taxonomy is the classification system used by the European Union to guide private investment toward environmentally sustainable economic projects.)
In his annual State of the State Address on January 31, Tennessee Gov. Bill Lee offered more praise for nuclear energy, after lauding it earlier in the month during a tour of the Tennessee Valley Authority’s Watts Bar nuclear plant
“For decades, East Tennessee has been home to some of the best-kept secrets in nuclear energy and American innovation,” Lee told the state’s General Assembly. “Today, many may not realize that Tennessee derives more power from nuclear energy than from any other source. Recently, I visited the TVA’s Watts Bar nuclear facility, the last nuclear facility to be built in America, to see firsthand how nuclear power keeps our grid dependable even when the weather is not. Nuclear power is clean energy that actually works for the private sector.”
Alaska Gov. Mike Dunleavy (R.) introduced “An act relating to microreactors” (SB 177) in the Alaska state legislature on February 1 that would modify existing state law on nuclear energy by specifying that microreactors are not subject to certain nuclear reactor siting and permitting regulations in Alaska. The bill defines a microreactor as an advanced nuclear fission reactor that would be capable of generating no more than 50 MWe.
A spokesperson for Georgia Power has confirmed that the projected in-service date for the new Vogtle-3 reactor remains the third quarter of 2022, according to an article published on January 27 on the Power magazine website. The in-service date for Vogtle-4 is targeted for the second quarter of 2023, the spokesperson said.
During a tour last week of the Tennessee Valley Authority’s two-unit Watts Bar nuclear power plant in Tennessee, Gov. Bill Lee said, "Nuclear energy is so important not only because it is an important part of TVA's power generation but also because of the value that clean energy via nuclear energy can have for sustainability in this country,” according to an article in the Chattanooga Times Free Press.
Lee added that he would support TVA’s plans if it decided to build small modular reactors.
A new bill in the Indiana state Senate creates guidelines for state regulators to consider small modular reactors should utilities want to build them. Senate Bill 271 was sponsored by Sen. Eric Koch (R., Bedford), chair of the Senate Utilities Committee, and Sen. Blake Doriot (R., Goshen). Supporters of the bill said that SMRs could replace retiring coal plants and would supplement renewables.
The Indy Star reported on January 24 that the utilities committee passed the bill by a vote of eight to two and that it now heads to the full Senate.
The Intergovernmental Panel on Climate Change (IPCC)—the United Nations body established to assess the science related to climate change—is offering experts an opportunity to review the draft version of its Sixth Assessment Synthesis Report.
IPCC assessment reports are published every six to seven years. The Fifth Assessment Report, completed in 2014, provided the main scientific input to the 2015 Paris Agreement.
Interested experts can register for participation in the review here. Registration is open through March 13. The review period ends on March 20.
Despite last year’s announcement from EDF Energy that the startup of Unit 1 at Hinkley Point C would likely be delayed (from late 2025 to June 2026), current progress at the site is receiving praise from the U.K. government.
On January 13, Kwasi Kwarteng, secretary of state for business, energy, and industrial strategy, and Helen Whately, exchequer secretary of the treasury, toured the nuclear new-build project, accompanied by Jean Bernard Lévy, EDF’s chairman and chief executive.
The International Energy Agency’s newly published in-depth review of Canada’s energy policies, the first since 2015, urges the nation’s government to take more action in support of nuclear energy.
The 261-page report, Canada 2022 Energy Policy Review, released on January 13, features a 17-page section devoted to nuclear that includes four specific recommendations for Canada’s federal government:
Like many of you, I have dedicated my career to the advancement of nuclear energy. We chose this path because clean energy changes lives. If we want to reduce greenhouse gas emissions, end energy poverty, develop a U.S. power grid that is secure and resilient, and ensure national security, nuclear must be a significant part of the mix.
But let us acknowledge the reality of our situation. Nuclear power plants continue to close. New reactor projects are too often delayed by cost overruns and red tape. Not having solved the politics for a permanent repository, spent fuel sits at shut-down reactor sites.
We find ourselves perpetually running the hamster wheel, building paper reactors, and grinding our teeth as critics cloud public discourse by regurgitating old fears and clinging to the tired tropes of a bygone era.
The Nuclear Regulatory Commission’s announcement earlier this month that it was denying Oklo Power’s license application to build and operate its Aurora microreactor in Idaho caught a lot of people by surprise, not the least of whom were the people at Oklo.
France’s Flamanville-3 project, plagued by schedule setbacks and cost overruns for well over a decade (construction of the unit commenced in December 2007), will be delayed a bit longer and cost a bit more.
Électricité de France announced yesterday that fuel loading at the 1,600-MWe EPR has been pushed back from the end of this year to the second quarter of 2023. The delay increases the project’s cost at completion from €12.4 billion (about $14.2 billion) to €12.7 billion (about $14.5 billion), more than four times the initial estimate of €3.3 billion, according to EDF.