Versatility, leadership, and “the highest fast neutron flux in the history of ever”: Highlights from INL’s VTR webinar

November 2, 2020, 12:04PMNuclear News

Clockwise from top left are Craig Piercy, Ray Furstenau, Tom O’Connor, Sean McDeavitt, Tara Neider, and Judi Greenwald.

The Versatile Test Reactor’s conceptual design was approved in September, and a draft environmental impact statement could be released within the week. The completion of more project milestones leading to operation in 2026, however, will depend on congressional appropriations. An expert panel described the need for a state-of-the-art test reactor and the value that the VTR could bring to the U.S. nuclear R&D community over its 60-year lifetime during a recent webinar—“Advanced U.S. Nuclear Research and Development: A Briefing and Discussion on the VTR”—hosted by Idaho National Laboratory.

Craig Piercy, ANS executive director/CEO, moderated the webinar, introducing a project update from VTR executive director Kemal Pasamehmetoglu and facilitating a Q&A session with representatives of the Nuclear Regulatory Commission, the Department of Energy, universities, reactor developers, and the Nuclear Innovation Alliance. A recording of the October 29 webinar is available online. INL also has a video and information online on the VTR.

“I think that the VTR represents part of a larger effort to modernize our infrastructure, develop a new set of technologies, and really preserve our global leadership in the field,” said Piercy. Read on to learn more about the promise the VTR holds for the nuclear community.

U-233 processing restarts at Oak Ridge following upgrades

October 22, 2020, 7:01AMNuclear News

A fissile material handler uses a shielded glovebox to dissolve U-233 into a low-level form so that it can be mixed with grout for safe transportation and disposal. Photo: DOE

The processing and downblending of uranium-233 for disposal has resumed at Oak Ridge National Laboratory, following a pause in operations due to the COVID-19 pandemic, the Department of Energy announced on October 20. Removal and disposition of the U-233 is one of the DOE Office of Environmental Management’s highest priorities at the site, as stated in its strategic vision released earlier this year.

The project is removing a significant risk by eliminating the inventory of highly enriched fissile material stored in Building 3019, the world’s oldest operating nuclear facility, according to the DOE. Employees, known as fissile material handlers, use shielded gloveboxes to dissolve U-233 into a low-level form so that it can be mixed with grout for safe transportation and disposal. The material dates back decades and was originally pursued as a fuel for reactors; however, it did not prove to be a viable option.

It’s time for the United States to demonstrate advanced reactors

October 16, 2020, 9:04AMANS Nuclear CafeRita Baranwal

After talking about it for decades, the United States is finally ready to take the next step in demonstrating advanced reactor technologies.

We have the bipartisan support from Congress. We have the best innovators in the world. Now it’s time to see what U.S. nuclear companies can really do with the support and resources of the federal government.

The U.S. Department of Energy is all in on new nuclear technologies and we just made our boldest move yet—selecting and supporting two U.S. reactor designs that will be fully operational within the next 7 years.

After evaluating the competitive U.S. reactor design applications that were submitted to our new Advanced Reactor Demonstration Program funding opportunity announcement, TerraPower LLC and X-energy were awarded $160 million in initial funding to test, license, and build their advanced reactors under this aggressive timeframe. Pending future appropriations by Congress, the DOE will invest $3.2 billion over 7 years in these projects that will be matched by the industry teams.

ARDP picks divergent technologies in Natrium, Xe-100: Is nuclear’s future taking shape?

October 14, 2020, 7:21AMNuclear News

The Department of Energy has put two reactor designs—TerraPower’s Natrium and X-energy’s Xe-100—on a fast track to commercialization, each with an initial $80 million in 50-50 cost-shared funds awarded through the Advanced Reactor Demonstration Program (ARDP). In all, the DOE plans to invest $3.2 billion—with matching funds from industry—over the seven-year demonstration program, subject to future appropriations.

Energy Secretary Dan Brouillette announced the awards late in the day on October 13 in Oak Ridge, Tenn., and said, “These awards are a critical first step of a program that will strengthen our nation’s nuclear energy and technological competitiveness abroad, and position our domestic industry for growth, for increased job creation, and for even more investment opportunity. It’s absolutely vital that we make progress on this technology now.”

“Critical decision” keeps Versatile Test Reactor on target

September 24, 2020, 3:05PMNuclear News

The proposed Versatile Test Reactor complex would cover about 20 acres. Image: INL

Now that the Department of Energy has approved Critical Decision 1 for the Versatile Test Reactor (VTR) project, the engineering design phase can begin once Congress appropriates funding, according to a September 23 announcement from the DOE’s Office of Nuclear Energy. The DOE has requested $295 million for the project in fiscal year 2021.

The news came nearly one month after a team led by Bechtel National Inc. (BNI), and including GE Hitachi Nuclear Energy (GEH) and TerraPower, entered into contract negotiations with Battelle Energy Alliance (BEA) for the design-and-build phase of the VTR. GEH’s sodium-cooled fast reactor PRISM technology was selected to support the VTR program in November 2018.

TerraPower, Centrus, and Duke Energy talk tech and collaboration

September 23, 2020, 3:01PMNuclear News

Three companies that are part of a larger collaboration to develop and demonstrate Natrium, the fast reactor design recently introduced by TerraPower and GE Hitachi Nuclear Energy (GEH), were invited to participate in a webinar hosted by ClearPath to talk about Natrium’s design, fuel requirements, and load-following potential.

The September 21 webinar, titled “Natrium: Latin for Sodium, Big for Advanced Nuclear,” was moderated by Rich Powell, executive director of ClearPath, and featured TerraPower’s Chris Levesque and Tara Neider, Centrus Energy’s Dan Poneman, and Duke Energy’s Chris Nolan.

HALEU investment is key part of TerraPower’s demo proposal

September 17, 2020, 2:58PMNuclear News

TerraPower announced on September 15 that it plans to work with Centrus Energy to establish commercial-scale production facilities for the high-assay, low-enriched uranium (HALEU) needed to fuel many advanced reactor designs.

The proposed investment in HALEU fuel fabrication is tied to a TerraPower-led submittal to the Department of Energy’s Advanced Reactor Demonstration Program (ARDP), which was created to support the deployment of two first-of-a-kind advanced reactor designs within five to seven years. TerraPower would like one of those designs to be Natrium, the 345-MWe sodium fast reactor that it has developed with GE Hitachi Nuclear Energy.

TerraPower’s Natrium pairs a sodium fast reactor with heat storage

September 2, 2020, 3:00PMNuclear News

An artist’s rendering of Natrium. Image: TerraPower

The Natrium reactor and energy system architecture, recently introduced by TerraPower and GE Hitachi Nuclear Energy (GEH), offers baseload electricity output from a 345-MWe sodium fast reactor with the load-following flexibility of molten salt thermal storage. Stored heat can be used to boost the system’s output to 500 MWe for more than five and a half hours when needed, according to TerraPower. A company representative told Nuclear News that the company expects a commercial Natrium plant to cost $1 billion or less.

Negotiations to build Versatile Test Reactor under way

August 27, 2020, 7:05AMNuclear News

Artist’s rendering of the Versatile Test Reactor. INL Image

A team led by Bechtel National Inc. (BNI) that includes GE Hitachi Nuclear Energy (GEH) and TerraPower is in contract negotiations with Battelle Energy Alliance (BEA) for the design-and-build phase of the Versatile Test Reactor, BEA announced on August 24. As planned, the VTR would support irradiation testing of fuels, materials, and equipment designed for advanced reactors.

TerraPower looks to turn DOE’s waste uranium into actinium-225

August 5, 2020, 10:12AMAround the Web

This vial contains traces of actinium within a mixture of thorium and uranium. Photo: Isotek

An article recently published in Chemical & Engineering News describes TerraPower’s efforts to extract actinium-225, a radioisotope with therapeutic potential, from highly radioactive uranium-233 owned by the Department of Energy and slated for disposal. While others are working to ramp up production of Ac-225 by using a linear accelerator or cyclotron, TerraPower hopes to harvest between 200,000 and 600,000 doses a year from U-233 to increase the global supply.

Nuclear Video Matinee: NuScale and TerraPower at CERAWeek

April 11, 2014, 6:00AMANS Nuclear Cafe

ICOSA Media caught up with NuScale chief executive officer Chris Colbert and TerraPower CEO John Gilleland at the recent CERAWeek energy conference in Houston, Tex. The two leaders of these innovative nuclear energy companies discuss the how's and why's of their small and beautiful reactor designs-the NuScale Small Modular reactor and the TerraPower Traveling Wave reactor.