Waste Management


Hanford pours first glass from Vit Plant melter

November 8, 2023, 9:30AMRadwaste Solutions
Workers monitor the pouring of melter glass from a control room in Hanford’s LAW Facility. (Photo: DOE)

The Department of Energy’s Office of Environmental Management said crews at its Hanford Site in Washington state have started pouring the first molten glass from a waste vitrification melter into a stainless steel container at the site’s Waste Treatment and Immobilization Plant, also known as the Vit Plant.

The safe plan for Japan’s wastewater

November 7, 2023, 3:00PMNuclear NewsKen Petersen

Ken Petersen
president@ans.org

There has been a lot of breathless coverage surrounding the release of mildly tritiated wastewater from the Fukushima Daiichi site, generated in no small part by people, organizations, and even nations with a political axe to grind. But here are the facts:

On August 24, 2023, Fukushima Daiichi began its first release of tritium-containing water, following the Japanese government’s plans to meet all international guidelines. The International Atomic Energy Agency, which has established a permanent office at the plant, provided on-site observation, online monitoring, and an independent analysis of the release. (The IAEA will continue to do so for all future releases.) Tokyo Electric Power Company (TEPCO) reported that analyses of water samples taken from the sea within three kilometers of the plant showed tritium concentrations below 10 becquerels per liter, well below the 700 becquerels per liter set by the utility for suspending the release, and substantially below the drinking water quality standard of 10,000 becquerels per liter set by the World Health Organization.

Hanford upgrades its Effluent Treatment Facility

November 7, 2023, 9:31AMRadwaste Solutions
The Hanford Site’s ETF has been expanded. (Photo: DOE)

The Hanford Site’s Effluent Treatment Facility (ETF) has been expanded and will be able to handle almost 7 million more gallons of wastewater per year once the site’s Waste Treatment and Immobilization Plant (WTP) begins treating waste from large underground tanks.

SHINE looks to license used fuel recycling facility

November 1, 2023, 12:12PMRadwaste Solutions
A spent nuclear fuel transportation container. (Photo: DOE)

Fusion systems company SHINE Technologies has notified the Nuclear Regulatory Commission that it intends to submit a license application to build and operate a pilot used nuclear fuel recycling facility.

EPRI joins NEA in joint advanced reactor waste project

October 31, 2023, 9:31AMRadwaste Solutions
NEA director general William Magwood (left) and EPRI senior vice president Neil Wilmshurst finalize EPRI support for the joint WISARD project. (Photo: NEA)

The Nuclear Energy Agency has announced a new collaboration with the Electric Power Research Institute on an upcoming project that will focus on waste management strategies for small modular reactors and advanced nuclear energy systems.

NRC approves emergency planning exemptions for defueled Indian Point

October 30, 2023, 9:52AMRadwaste Solutions
Indian Point nuclear power plant. (Photo: Daniel Case)

The Nuclear Regulatory Commission hasgranted a request by Holtec Decommissioning International (HDI) to revise the emergency preparedness plan for the Indian Point Energy Center. Reflecting the reduced risk of a radiological emergency at a decommissioning power reactor site, the exemption removes the requirement that HDI maintain a 10-mile emergency planning zone around the plant.

U.S. requests review of circuit court’s ruling on Texas storage facility

October 27, 2023, 12:05PMRadwaste Solutions

The Nuclear Regulatory Commission and the U.S. Department of Justice are asking the 5th U.S. Circuit Court of Appeals to review its decision to vacate Interim Storage Partners’ license to build and operate a consolidated interim storage facility (CISF) for commercial spent nuclear fuel in Andrews County, Texas.

New LLW sorting facility opens in Ontario

October 26, 2023, 9:30AMRadwaste Solutions
Representatives from OPG, Laurentis Energy Partners, and EnergySolutions Canada, as well as the mayor of Kincardine, Kenneth Craig, cut the ceremonial ribbon to officially open WCSR facility. (Photo: OPG)

Ontario Power Generation (OPG) subsidiary Laurentis Energy Partners has opened, in partnership with EnergySolutions Canada, a new 42,000-square-foot facility in Kincardine, Ontario, that will minimize waste associated with nuclear energy generation in the Canadian province, the company announced this week.

Progress touted in D&D of Idaho’s naval nuclear prototypes

October 25, 2023, 12:04PMRadwaste Solutions
Crews demolish one of two massive steam condensers at the Naval Reactors Facility’s A1W prototype reactor facility in Idaho. Click photo to enlarge (Photo: DOE)

The Department of Energy’s Office of Environmental Management said that crews at the Idaho National Laboratory site are making “significant progress” decommissioning the Submarine 1st Generation Westinghouse (S1W) reactor, the prototype pressurized water reactor that supported the development of the USS Nautilus, the world’s first operational nuclear-powered submarine.

Holtec completes Indian Point dry storage campaign

October 24, 2023, 12:03PMRadwaste Solutions
The Indian Point fuel campaign crew at the plant ISFSI. (Photo: Holtec)

Holtec International marked a milestone last week in its decommissioning of Indian Point Energy Center with the transfer of all the plant’s spent nuclear fuel to dry storage. According to the company, the last fuel assembly from Indian Point-3 was placed into dry cask storage at 2:22 a.m. on October 14.

Share:

DOE seeks input on Hanford’s 5-year cleanup plan

October 16, 2023, 12:40PMRadwaste Solutions
Crews with Hanford contractor Central Plateau Cleanup Company break up concrete and remove contaminated soil near the former K Area reactors on the Hanford Site earlier this year. (Photo: DOE)

The Department of Energy is seeking the public’s input on the Hanford Site’s 5-year plan, which outlines planned cleanup work either to be completed or initiated at the former plutonium production site near Richland, Wash. The DOE updates Hanford’s 5-year plan annually to reflect current progress and ongoing integrated planning for future work at the site.

New Mexico approves WIPP’s 10-year permit renewal

October 12, 2023, 9:31AMRadwaste Solutions
Mining crews view progress in an ongoing mining tunnel, known as a drift, at the WIPP facility in New Mexico. (Photo: DOE)

The New Mexico Environment Department (NMED) signed a final order approving a 10-year permit renewal for the Waste Isolation Pilot Plant (WIPP), the nation’s deep geologic repository for defense-related transuranic (TRU) waste.

Oak Ridge seeing returns on investment in new regulatory partnerships

October 11, 2023, 12:09PMRadwaste Solutions
Contaminated soil is loaded in containers for disposal at the Oak Ridge Reservation in Tennessee. (Photo: DOE)

The Department of Energy’s Office of Environmental Management said a new regulatory partnership framework established in recent years by the Oak Ridge Office of Environmental Management (OREM), its contractor United Cleanup Oak Ridge (UCOR), the Environmental Protection Agency, and the Tennessee Department of Environment and Conservation (TDEC) is ushering in a new chapter of accelerated cleanup at the department’s Oak Ridge Reservation in Tennessee.

Canada to site a geologic repository for ILW and nonfuel HLW

October 10, 2023, 3:01PMRadwaste Solutions

The Nuclear Waste Management Organization, the not-for-profit organization responsible for managing Canada’s spent nuclear fuel, said it will begin developing a plan for a consent-based siting process for a deep geologic repository for intermediate-level and nonfuel high-level radioactive waste.

What Texas v. Nuclear Regulatory Commission tells us

October 9, 2023, 12:00PMNuclear NewsCraig Piercy

Craig Piercy
cpiercy@ans.org

Here we go again: Another “workaround” on U.S. nuclear waste policy just got shot down in a federal courtroom. On August 25, the 5th U.S. Circuit Court of Appeals found that the Nuclear Regulatory Commission lacked the authority to grant a license to Interim Storage Partners LLC (read: Waste Control Specialists) to accept and store up to 5,000 tons of used nuclear fuel at its proposed facility in Andrews County, Texas. Writing for the court, U.S. circuit judge James Ho found that “the Nuclear Waste Policy Act (NWPA) creates a comprehensive statutory scheme for addressing spent nuclear fuel accumulation. The scheme prioritizes construction of the permanent repository and limits temporary storage to private, at-the-reactor storage or at federal sites. It plainly contemplates that, until there’s a permanent repository, spent nuclear fuel is to be stored onsite at-the-reactor or in a federal facility.”

This decision is not necessarily a knockout blow. The court’s reading of the law is, well, novel. Other appeals courts have recognized the NRC’s authority to license away-from-reactor storage, and the Supreme Court is likely to weigh in. But given the current high court’s proclivities on “textualism” and the Chevron doctrine, we shouldn’t consider it a slam dunk.

SRS employees use novel training exercise to align waste mission

October 5, 2023, 3:02PMRadwaste Solutions
Ray Tran, an engineer for Savannah River tank farms, helps complete a timeline of SRS historical events as part of SRMC’s vision casting training initiative. (Photo: DOE)

More than 3,000 employees with Department of Energy contractor Savannah River Mission Completion (SRMC) participated in a vision casting initiative, learning more about the past, present, and future of the Savannah River Site’s liquid waste mission.

Crews demolish second legacy Oak Ridge reactor lab

October 2, 2023, 3:00PMRadwaste Solutions
The Low Intensity Test Reactor structure is lifted from its housing and placed in a specialized carbon metal container for shipment for disposal. (Photo: DOE)

The Department of Energy’s Office of Environmental Management announced it has completed a second of its 2023 priorities at Oak Ridge in as many months with the demolition of the Low Intensity Test Reactor, known as Building 3005, at the Tennessee site.

Watch a video of Building 3005 and its decommissioning here.

DOE-EM awards cleanup grants and cooperative agreements

October 2, 2023, 9:30AMRadwaste Solutions
Workers remove contaminated sediment from the SRS in South Carolina. A $19 million DOE grant will support state monitoring of the site. (Photo: DOE)

The Department of Energy’s Office of Environmental Management has awarded nearly $54 million in noncompetitive financial assistance grants and cooperative agreements to help support the office’s cleanup program. DOE-EM is responsible for environmental legacy cleanup of the effects of decades of nuclear weapons development and government-sponsored nuclear energy research.

Washington reaches settlement with DOE in Hanford data access spat

September 19, 2023, 9:32AMRadwaste Solutions
A Department of Ecology inspector at the Hanford Site. (Photo: Department of Ecology)

Washington state’s Department of Ecology said it has reached a settlement with the Department of Energy over access to data the state described as “critical” to the cleanup of the Hanford Site near Richland, Wash.

SEC files lawsuit against nuclear battery startup

September 18, 2023, 12:00PMRadwaste Solutions

The Securities and Exchange Commission is suing nuclear battery developer NDB Inc., charging that the company and its chief executive officer, Nima Golsharifi, defrauded investors by making materially false and misleading statements in a company press release.