Decontamination and Decommissioning


Norway’s Halden reactor takes first step toward decommissioning

April 1, 2025, 3:00PMRadwaste Solutions
The reactor hall of the Halden research reactor in Norway. (Photo: IFE)

The government of Norway has granted the transfer of the Halden research reactor from the Institute for Energy Technology (IFE) to the state agency Norwegian Nuclear Decommissioning (NND). The 25-MWt Halden boiling water reactor operated from 1958 to 2018 and was used in the research of nuclear fuel, reactor internals, plant procedures and monitoring, and human factors.

NorthStar closes on Vallecitos D&D agreement

March 18, 2025, 7:06AMRadwaste Solutions
The Vallecitos Nuclear Center site in northern California. (Photo: NRC/Don Sleeter)

NorthStar Group Services has announced that it has closed on an agreement to acquire ownership of the Vallecitos Nuclear Center from GE Vernova and GE Hitachi Nuclear Energy for NorthStar's nuclear decontamination, decommissioning, and environmental site restoration.

West Valley shares 3D model and lessons learned

March 12, 2025, 12:00PMRadwaste Solutions
A 3D model shows areas of West Valley's main plant process building demolition project that have been completed in yellow. Workers have removed 52 of the building’s 56 cells since the start of the demolition in September 2022.(Image: DOE)

A virtual meeting between representatives of the West Valley Demonstration Project (WVDP) in New York and the Oak Ridge Office of Environmental Management (OREM) in Tennessee was held recently to share lessons learned from the ongoing demolition of West Valley’s main plant process building.

NRC report updates decommissioning cost guidance

February 19, 2025, 12:00PMRadwaste Solutions

The Nuclear Regulatory Commission has updated its guidance for nuclear power plant owners and operators in estimating the cost of decommissioning their reactors. Licensed power reactor operators are required under NRC regulations to annually adjust the estimated costs (in current year U.S. dollars) of decommissioning their plants to ensure that adequate funds are available when needed.

Los Alamos begins project to remove historic facility

February 6, 2025, 7:01AMRadwaste Solutions
The Ion Beam Facility, center, at Technical Area 03 at LANL. (Photo: DOE)

Work has started at the Department of Energy’s Los Alamos National Laboratory in New Mexico to deactivate, decommission, and remove the Ion Beam Facility, which played a role in research and experiments that helped develop the nation’s nuclear arsenal during the 1950s and 1960s.

Hanford pauses D&D prep work on REDOX facility

December 16, 2024, 3:00PMRadwaste Solutions
Demolition work being conducted on Hanford’s REDOX facility in July 2024. (Photo: DOE)

Work to prepare Hanford’s Reduction Oxide Plant (REDOX) for decontamination and demolition has been put on hold as the Department of Energy shifts focus to higher-priority work at the nuclear site in Washington state.

Drones fly in to inspect waste tanks at Savannah River Site

November 27, 2024, 3:01PMNuclear News
The Flyability Elios 3 model drone for the SRS tank inspection program. (Photo: SRS)

The Department of Energy’s Office of Environmental Management will soon, for the first time, begin using drones to internally inspect radioactive liquid waste tanks at the department’s Savannah River Site in South Carolina. Inspections were previously done using magnetic wall-crawling robots.

History in the making: D&D begins on Three Mile Island-2

November 8, 2024, 3:12PMNuclear News
A 3D, semitransparent model of the TMI-2 reactor building is helping planners and workers visualize the work to be done in the radiologically controlled building. (All photos: Tim Gregoire)

Constellation Energy has announced that it will seek to restart Unit 1 of the Three Mile Island nuclear power plant in Pennsylvania as part of an agreement with Microsoft to power that company’s data centers. Given the growing interest by tech companies in using clean, reliable nuclear power to meet their growing energy demands, the September 20 announcement to reopen TMI-1, which was shut down and defueled in 2019, was not a huge surprise.

Huff shares insight into restarting decommissioned reactors

October 31, 2024, 9:30AMANS Nuclear Cafe
An aerial photo of Three Mile Island nuclear power plant. (Photo: Constellation)

The pursuit of returning two of the country’s retired nuclear plants into service is not only unusual—it is unprecedented and promises to make history.

That’s according to a piece coauthored by former assistant secretary for nuclear energy Katy Huff in the Bulletin of the Atomic Scientists regarding plans from Holtec and Constellation to restart Michigan’s Palisades plant and Pennsylvania’s Three Mile Island Unit 1, respectively.

Amentum to consult on Ignalina decommissioning

October 31, 2024, 7:01AMRadwaste Solutions
The Ignalina nuclear power plant in Lithuania. (Photo: INPP)

Chantilly, Va.-based Amentum has been awarded a 7-year contract estimated to be worth €5.5 million (about $6 million) to consult on the dismantling of steam drum separators in Units 1 and 2 of Lithuania’s Ignalina nuclear power plant. Once the country’s largest generator of electricity, Ignalina was permanently shut down in 2009 and the plant’s two RBMK-1500 reactors are expected to be fully decommissioned by 2038.

Ship shape: Dismantling the Navy’s surface ship support barge

October 29, 2024, 7:03AMRadwaste SolutionsBruce Fox, David Lowe, Jack Reust, and Sean McCutcheon
The U.S. Navy’s Surface Ship Support Barge arrives in Mobile, Ala., for demolition after being towed by sea from Virginia. (Photos: APTIM)

The U.S. Navy’s Surface Ship Support Barge, converted in the 1960s from a WWII T2 tanker to a support barge to accept spent nuclear fuel during the refueling of nuclear aircraft carriers, was dismantled and disposed of by the nuclear decommissioning company APTIM as a first-of-its-kind vessel dismantlement project for the Navy. The project was executed under contract with Naval Sea Systems Command; however, regulatory oversight was accomplished through an interagency framework agreement between the U.S. Navy and the Nuclear Regulatory Commission.

Sellafield not “achieving value for money,” according to U.K. watchdog

October 25, 2024, 12:00PMRadwaste Solutions
The Sellafield nuclear site in Cumbria, England. (Photo: NEA/OECD)

Despite progress made over the past years, the United Kingdom’s Nuclear Decommissioning Authority (NDA) has not seen an adequate return on investment in cleaning up the Sellafield nuclear site on England’s Cumbria coast, according to a new report by the U.K.’s National Audit Office, which scrutinizes government spending.

DOE plans removal of naval prototype reactor, opens public comment period

October 17, 2024, 12:00PMRadwaste Solutions
The S5G prototype, which was constructed to simulate submarine operations and could mimic ocean-like conditions, is positioned inside a subgrade basin. (Photo: IEC)

The Department of Energy is proposing to fully decommission the Submarine 5th Generation General Electric (S5G) prototype at the Naval Reactors Facility on the Idaho National Laboratory site. Along with the Environmental Protection Agency and the state of Idaho, the DOE has initiated a 30-day public comment period (ending November 14) on the planned end state for the facility and its defueled reactor vessel.

The D&D of SM-1A

October 11, 2024, 3:00PMRadwaste SolutionsThe U.S. Army Corps of Engineers, Baltimore District
A team member wearing a powered air-purifying respirator prepares to enter the SM-1A vapor containment structure. (Photo: USACE/David Gray)

With the recent mobilization at the site of the former SM-1A nuclear power plant at Fort Greely, Alaska, the Radiological Health Physics Regional Center of Expertise, located at the U.S. Army Corps of Engineers’ Baltimore District, began its work toward the decommissioning and dismantlement of its third nuclear power plant, this time located just 175 miles south of the Arctic Circle.

The Cumbria Robotics Cluster: Bolstering innovation and collaboration in the U.K.

October 10, 2024, 1:25PMRadwaste Solutions
The JCB excavator robot developed by Forth Engineering for the Sellafield nuclear site.

Robotics is fast becoming a go-to for nuclear decommissioning advances, and several organizations working in West Cumbria, England, the hub of the United Kingdom’s energy sector, have formed a partnership to share insight and work together to address common challenges and opportunities. Cumbria Robotics Cluster is an ambitious initiative powered by the Industrial Solutions Hub (iSH) to harness and expand the region’s renowned capabilities in cutting-edge engineering and problem solving.

Keeping up with Kewaunee

October 4, 2024, 3:14PMRadwaste Solutions
Wisconsin’s Kewaunee nuclear power plant as it appeared in May of this year. A number of ancillary buildings have already been demolished and their waste removed. The intermodal waste transportation staging areas can be seen to the left. The site ISFSI is out of view to the right. (Photo: EnergySolutions)

In October 2012, Dominion Energy announced it was closing the Kewaunee nuclear power plant, a two-loop 574-MWe pressurized water reactor located about 27 miles southeast of Green Bay, Wis., on the western shore of Lake Michigan. At the time, Dominion said the plant was running well, but that low wholesale electricity prices in the region made it uneconomical to continue operation of the single-unit merchant power plant.

NRC seeks input on DRP contamination guidance

September 30, 2024, 9:30AMRadwaste Solutions

The Nuclear Regulatory Commission is soliciting public comment on the agency’s guidance for addressing discrete radioactive particle (DRP) contamination resulting from the decontamination and decommissioning of nuclear facilities. According to the NRC, the draft guidance is intended to avoid any inconsistencies in how the agency approaches DRP contamination.

UK awards £30 million to advance decommissioning R&D

August 21, 2024, 9:31AMRadwaste Solutions
The Sellafield nuclear site in Cumbria, England. (Photo: Simon Ledingham)

The Nuclear Decommissioning Authority (NDA), the government agency charged with cleaning up the United Kingdom’s nuclear sites, has awarded three contracts totaling £30 million (about $39 million) for research into new decommissioning techniques.

Segmentation of Italy’s Garigliano reactor vessel continues

August 5, 2024, 7:00AMRadwaste Solutions
Remote equipment is used to remove components from the Garigliano reactor vessel. (Photo: Sogin)

Sogin (Società Gestione Impianti Nucleari), the state-owned company responsible for the decommissioning of Italy’s nuclear plants and the management of radioactive waste, announced on July 30 that it has completed the first phase of dismantling Garigliano nuclear power plant’s reactor vessel with the removal of contaminated metal components from the deflector.

Aptim wins $630 million contract for cleanup of naval reactor sites

June 28, 2024, 9:40AMRadwaste Solutions

The Department of Energy’s Office of Environmental Management awarded a 10-year contract worth up to $630 million to Louisiana-based Aptim Federal Services for deactivation and decommissioning work at two U.S. Naval Nuclear Propulsion Program sites in New York.