ITER leaders outline plan for component repairs and replacements

January 11, 2023, 12:00PMNuclear News
The cooling pipes that snake along the surface of the vacuum vessel thermal shield will be removed and replaced. Here, on a right-hand outboard panel, workers determine the impact of pipe removal on the surface of the component. (Photo: ITER Organization)

ITER’s machine assembly phase began about two and a half years ago. Now, staff are reversing some of that assembly work to make needed repairs. According to a news article published by the ITER Organization on January 9, ITER is “facing challenges common to every industrial venture involving first-of-a-kind components.” Over one year after problems were first detected and less than two months after they were made public in late November, tests and analysis are producing a clearer picture of necessary repairs to the tokamak’s thermal shield panels and vacuum vessel sectors.

“There is no scandal here,” said ITER director general Pietro Barabaschi. “Such things happen. I've seen many issues of the kind, and much worse.”

Stress corrosion cracking and welding nonconformities are behind ITER’s fresh delays

December 5, 2022, 3:00PMNuclear News
A total of about 23 kilometers (about 14 miles) of piping are welded to the surface of the thermal shield panels. The piping on a vacuum vessel thermal shield panel is clearly visible in this photo. (Photo: ITER Organization)

The ITER Organization is working on a new baseline schedule for the magnetic confinement fusion experiment launched in 1985 and now under construction in southern France. First plasma was scheduled for December 2025 and deuterium-tritium operations for 2035 under a schedule approved in November 2016 that will soon be shelved. In addition to impacts from COVID-19 delays and uncertainty resulting from Russia’s war in Ukraine, ITER leaders must now factor in repair time for “component challenges.”

Fusion veteran Barabaschi selected as ITER director general

September 23, 2022, 7:00AMANS Nuclear Cafe

Barabaschi

Capping a session in Paris, the ITER Council has unanimously selected Pietro Barabaschi as the new director-general of the ITER Organization. The Italian-born Barabaschi, who has been involved in nuclear fusion research for some 30 years, was chosen to lead the massive international fusion project following an intensive recruitment effort necessitated by the death of Bernard Bigot, the previous director general, in May. Since Bigot’s death, Eisuke Tada has been serving in the role in an interim capacity. Barabaschi will take office in October.

F4E leader: Barabaschi has been the head of the Broader Approach Programme and Delivery with Fusion for Energy (F4E) since 2008. F4E is the EU organization responsible for Europe’s contribution to ITER. In this position, he has been managing the department that oversees three projects stemming from the Broader Approach agreement between the European Atomic Energy Community (Euratom) and the government of Japan: the JT-60SA tokamak, the International Fusion Materials Irradiation Facility/Engineering Validation and Engineering Design Activities linear accelerator, and the International Fusion Energy Research Centre . Barabaschi has also been acting director of F4E.