Tank waste operations resume at Idaho’s IWTU

September 18, 2024, 3:00PMRadwaste Solutions
Crews with the Idaho National Laboratory Site’s IWTU replace filter bundles inside the unit’s process gas filter. (Photo: DOE)

The Department of Energy’s Office of Environmental Management announced yesterday that waste processing operations have resumed at the Integrated Waste Treatment Unit (IWTU) at the Idaho National Laboratory Site. The resumption of operations follows the completion of two maintenance campaigns at the radioactive liquid waste treatment facility.

2023 in Review: April–June

January 11, 2024, 7:00AMNuclear News

Another calendar year has passed. Before heading too far into 2024, let’s look back at what happened in 2023 in the nuclear community. In today's post, compiled from Nuclear News and Nuclear Newswire are what we feel are the top nuclear news stories from April through June 2023.

Stay tuned for the top stories from the rest of the past year.

Idaho’s IWTU to resume operations in early 2024

December 14, 2023, 9:30AMRadwaste Solutions
A view of two vessels that each contain approximately 30,000 pounds of granulated activated carbon, used to remove mercury from process off-gas during IWTU operations. (Photo: DOE)

The Department of Energy’s Office of Environmental Management said Idaho’s Integrated Waste Treatment Unit (IWTU) is set to resume radioactive liquid waste treatment operations early next year after crews replaced carbon material from two plant vessels. The IWTU was shut down for an unplanned outage on September 6 to address elevated mercury concentrations in the plant’s granulated activated carbon (GAC) beds, according to Defense Nuclear Facilities Safety Board (DNFSB) reports.

Idaho’s IWTU reaches 100 percent radiological operations

May 25, 2023, 12:00PMRadwaste Solutions
DOE-EM’s Greg Sosson (standing) views Integrated Waste Treatment activity during the facility’s first day of radiological operations. (Photo: DOE)

After initial runs using a mix of radiological waste and nonradioactive simulant, the Integrated Waste Treatment Unit (IWTU) at the Idaho National Laboratory site has progressed to treating sodium-bearing waste entirely, the Department of Energy’s Office of Environmental Management (DOE-EM) announced on May 22.

INL waste treatment plant increases production

May 17, 2023, 12:00PMNuclear News
DOE-EM officials, IWTU employees, and others signed the first stainless steel canister prior to crews filling it with sodium-bearing waste and simulant. Once filled, that canister and 15 others were placed in a concrete vault for storage. (Photo: DOE)

Since the launch of operations just over a month ago, the Integrated Waste Treatment Unit (IWTU) at Idaho National Laboratory has increased sodium-bearing waste treatment fivefold. This activity is a vital step in removing the remaining liquid waste from nearby underground tanks at the site and protecting the underlying Snake River Plain Aquifer.

Radiological operations of Idaho’s IWTU begin

April 12, 2023, 3:08PMRadwaste Solutions

IWTU operators prepare to introduce radiological sodium-bearing liquid waste into the facility Tuesday. (Photo: DOE)

More than a decade after construction was declared completed, Idaho’s long-delayed Integrated Waste Treatment Unit (IWTU) has begun radiological operations, the Department of Energy’s Office of Environmental Management (EM) announced.

On Tuesday, crews at the Idaho National Laboratory Site began sending radioactive sodium-bearing liquid waste from nearby underground tanks to the IWTU for treatment. The 900,000 gallons of waste was generated during decontamination activities following spent nuclear fuel reprocessing that ended in 1992.

The IWTU uses steam reforming fluidized-bed reactor technology to convert liquid waste to a granular solid resembling coarse sand more suitable for long-term disposal.

Idaho’s IWTU resumes heat-up following repairs

February 2, 2023, 7:01AMRadwaste SolutionsJohn Fabian

The Department of Energy’s Office of Environmental Management (EM) said that heat-up of Idaho’s Integrated Waste Treatment Unit (IWTU) resumed in January. Crews began heating the IWTU in December in preparation of radiological operations, but the facility was shut down 10 days later after operators noticed a small leak of nonradioactive material inside one of the unit’s processing cells.

Located at the DOE’s Idaho National Laboratory Site, the IWTU is intended to treat Idaho’s 900,000 gallons of sodium-bearing liquid waste, converting it to a solid using a steam-reforming process.

After repairs were made to the IWTU equipment responsible for the leak, crews removed a partial obstruction that was in a line into the carbon reduction reformer, a key treatment vessel in the steam-reforming process, EM said.

Cell leak delays startup of Idaho’s IWTU

January 19, 2023, 7:00AMRadwaste Solutions

Ten days after beginning a heat-up process to prepare for radiological operations at Idaho’s Integrated Waste Treatment Unit (IWTU), operators noticed a small leak of nonradioactive, nonhazardous solids in a cell, resulting in the facility’s shutdown in late December, the Department of Energy announced on January 10.

Idaho’s IWTU prepares for radiological operations

January 6, 2023, 3:00PMRadwaste Solutions
The Integrated Waste Treatment Unit at the Idaho National Laboratory Site. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) said that the Integrated Waste Treatment Unit (IWTU), the radioactive liquid waste treatment facility at the Idaho National Laboratory Site, began its final heat-up in December prior to initiating radiological operations, planned for early this year.

IWTU crews were to follow a prescribed incremental process as the facility transitions from simulant to sodium-bearing waste (SBW), according to EM.

Idaho completes test run of liquid waste treatment facility

July 14, 2022, 7:00AMRadwaste Solutions
Workers inspect the IWTU’s process gas filter before the current confirmatory run. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) said it continues to make progress toward the start of operations of the Idaho National Laboratory Site’s Integrated Waste Treatment Unit (IWTU), having completed a final test run of the facility.

Operation of the IWTU, which was constructed to treat approximately 900,000 gallons of radioactive liquid waste, has been delayed a number of times, most recently due to supply chain issues.

Final test run begins on Idaho’s IWTU after supply chain delays

February 25, 2022, 7:13AMRadwaste Solutions
The IWTU liquid nitrogen storage system at the DOE’s Idaho National Laboratory Site. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) stated on February 22 that its Idaho National Laboratory Site contractor is operating the final test run of the Integrated Waste Treatment Unit (IWTU), running waste simulant through the facility to ensure the plant’s performance and personnel proficiency for upcoming radiological operations.