Hunterston B Unit 3 to restart soon; plant to retire earlier than expected

September 1, 2020, 9:59AMNuclear News

Workers on the fueling machine at Hunterston B. Photo: EDF Energy

EDF Energy has received approval from the United Kingdom’s Office for Nuclear Regulation (ONR) to restart the Hunterston B power station’s Unit 3 for a limited run, according to August 27 announcements from both the company and the regulator. EDF has permission to operate the unit for up to 16.425 terawatt days (approximately six months of operation), the ONR said.

EDF also announced that Hunterston B—located in North Ayrshire, along the western coast of Scotland—will begin its defueling phase no later than January 7, 2022, more than a year earlier than the expected retirement date of March 2023. The decision, EDF said, was made following a series of executive board and shareholders meetings.

EDF fined millions for disseminating misleading information about U.K. nuclear project

August 5, 2020, 3:21PMNuclear News

The Enforcement Committee of the Autorité des Marchés Financiers (AMF) has imposed a fine of €5 million (about $5.9 million) on Électricitéde France for providing false information about the Hinkley Point C new-build nuclear project in the United Kingdom. The committee has also imposed a €50,000 (about $59,000) fine on EDF’s former chairman and chief executive officer, Henri Proglio. According to a July 30 statement from the AMF, the false information was spread via an October 8, 2014, news release.

The AMF is described on its website as an independent public authority that regulates the French financial marketplace and its participants.

Exelon, EDF ask NY to okay proposed nuclear deal

July 28, 2020, 9:27AMNuclear News

Exelon Generation and Électricitéde France have asked the New York Public Service Commission to approve the transfer of EDF’s 49.99 percent ownership interest in Constellation Energy Nuclear Group (CENG) to Exelon, which owns 50.1 percent. CENG is the owner of New York’s Ginna and Nine Mile Point nuclear plants, as well as Maryland’s Calvert Cliffs.

New design center supports construction of Hinkley Point C

July 21, 2020, 9:38AMNuclear News

UK EPR Design Centre, Bristol, England. Image: EDF Energy

EDF Energy has opened a new engineering design facility in Bristol, England, to support the next phase of construction at the Hinkley Point C nuclear power station in Somerset, the company announced on July 14. The UK EPR Design Centre at Aztec West brings together nuclear designers and engineers from EDF and British engineering partners and suppliers, including Framatome UK, Atkins, Jacobs, Assystem, Anotech, and Vulcain, the announcement said.

France’s Fessenheim-2 closes permanently

July 1, 2020, 10:42AMNuclear News

Fessenheim nuclear power plant. Photo: EDF

After producing electricity generation for more than 40 years, Fessenheim-2 was disconnected from the grid on June 29, some four months after the retirement of its companion reactor, Fessenheim-1 (NN, Mar. 2020, p. 83). The action completes the closure of what had been France’s oldest operating nuclear power facility.

Both Fessenheim units are 880-MWe pressurized water reactors; Unit 1 began commercial operation in December 1977, with Unit 2 going on line in March 1978.

Base for second Hinkley Point C reactor completed

June 2, 2020, 3:42PMNuclear News

Concrete pour at the Hinkley Point C2 reactor. Photo: EDF Energy

Workers at the Hinkley Point C nuclear construction project in the United Kingdom have completed the 49,000-ton base for the station’s second reactor, Unit C2, hitting a target date set more than four years ago, according to EDF Energy.

EDF submits application to build Sizewell C station

June 1, 2020, 1:07PMNuclear News

Artist’s rendering of the Sizewell site, with Sizewell C at right. Image: EDF Energy

Électricité de France subsidiary EDF Energy has submitted an application to the United Kingdom government’s Planning Inspectorate for a development consent order (DCO) to build a new power station, Sizewell C, at the Sizewell nuclear site in Suffolk. The agency received the application on May 27, after it had been deferred for two months because of the COVID-19 pandemic.