The Vogtle-4 turbine building in March. (Photo: Georgia Power)
Georgia Power has announced another key milestone for the Vogtle nuclear expansion project near Waynesboro, Ga.—the completion of hot functional testing at Unit 4. This achievement marks another significant step toward commercial operation for the Generation III+ AP1000 reactor, which is projected to enter service late in the fourth quarter 2023 or in the first quarter 2024.
Vogtle Units 3 and 4 in February. (Photo: Georgia Power)
Unit 3 at the Vogtle nuclear power plant has been successfully synchronized and connected to the electric grid, Georgia Power announced on April 1. The unit—one of two Westinghouse-supplied AP1000s at the Waynesboro, Ga., plant’s nuclear expansion site—becomes the first new U.S. power reactor to start up in seven years.
Unit 3 at the Vogtle nuclear power plant. (Photo: Georgia Power)
Unit 3 at the Vogtle nuclear power plant has achieved initial criticality, Georgia Power announced yesterday. A key milestone on the way to the reactor’s commercial operation, initial criticality demonstrates that operators have safely started, for the first time, the nuclear reaction inside the unit. (Fuel loading at Vogtle-3 began last October.)
From left, Westinghouse Energy Systems president David Durham, Polskie Elektrownie Jądrowe president Tomasz Stępień, and Westinghouse Poland president Mirosław Kowalik sign a contract on February 22 to advance Poland’s nascent nuclear energy program. (Photo: Westinghouse Electric Company)
State-owned Polish utility Polskie Electrownie Jądrowe and U.S.-based Westinghouse on February 22 moved a step closer to their end goal—the deployment of multiple AP1000 reactors in Poland—with the signing of a contract covering front-end engineering, early procurement work, and program development.
Vogtle-4 in October. (Photo: Georgia Power)
Cold hydro testing of Unit 4 at the Vogtle plant’s nuclear expansion site has been completed, Georgia Power announced on December 7.
The Dukovany nuclear power plant. (Photo: CEZ Group)
A Westinghouse-Bechtel team, France’s EDF, and Korea Hydro & Nuclear Power have all submitted their initial bids for securing the contract to build a fifth reactor at the Czech Republic’s Dukovany plant, Czech utility ČEZ has announced.
Vogtle Unit 3 in September. (Photo: Georgia Power)
Georgia Power announced this morning that fuel loading at Vogtle-3 has commenced, marking an important milestone on what has proved to be a long and bumpy road to startup and commercial operation of the first new nuclear power reactors to be built in the United States in more than three decades. (Major work on the Vogtle-3 and -4 project began in 2012, with a price tag of $14 billion and scheduled unit start dates of 2016 and 2017. The project’s total cost is now expected to exceed $30 billion.)
Artist's rendering of an LFR plant. (Image: Westinghouse)
Westinghouse Electric Company and Ansaldo Nucleare have announced the signing of a cooperation agreement to develop a next-generation nuclear power plant based on lead-cooled fast reactor (LFR) technology.
Wholly owned by Italy’s Ansaldo Energia, Ansaldo Nucleare is involved in the production of high-tech nuclear components; the design and construction of new builds; decommissioning; and advanced research on radwaste management, fusion, fourth-generation plants, and small modular reactors. In addition, the firm played a significant role in the development of such Generation III technologies as Westinghouse’s AP600 and AP1000 reactors.
Under the agreement, Westinghouse and Ansaldo Nucleare will advance a common design to maximize synergies; combine experience in design, testing, and licensing; and align respective partner and supply-chain organizations.
Artist’s rendering of the Westinghouse Electric AP1000 modular reactor. (Image: Westinghouse)
New and immersive internship and development opportunities are being offered through a partnership of Westinghouse Electric Company and the Ukrainian nuclear energy utility Energoatom. Beginning this autumn, more than 60 opportunities will be available for Ukrainian nuclear energy professionals and graduate-level students.
An artist's rendering of the NuScale plant. (Image: NuScale Power)
The Nuclear Regulatory Commission has directed its staff to issue a final rule certifying NuScale Power’s small modular reactor design for use in the United States, the agency announced last Friday.
Certification of the Portland, Ore.–based SMR developer’s design will become effective 30 days after publication of the rule in the Federal Register. The design will be incorporated as Appendix G to 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.