America's first new commercial nuclear energy reactors in 30 years are under construction at the Virgil C. Summer Nuclear Generating Station in Fairfield County, South Carolina, and the Alvin W. Vogtle Electric Generating Plant in Burke County, Georgia.
Let's catch up with some of the amazing transformations going on at the V.C. Summer site, where construction of two new AP1000 reactors is well underway.
First, on March 11, 2013, after weeks of long shifts and a final weekend of working around-the-clock, workers at V.C. Summer completed placing the nuclear island basemat for Unit 2. This major milestone was the first new construction nuclear concrete poured in the U.S. in three decades.
Time-lapse of final 2 days of installation:
On April 3, 2013, another milestone: South Carolina Electric & Gas workers place the 581-ton CR10 module using the Heavy Lift Derrick. This module provides temporary support for the Unit 2 containment vessel bottom head.
Thanks to South Carolina Electric and Gas Company for producing these excellent video updates.
The Nuclear Regulatory Commission is asking for public feedback on the environmental report for a subsequent license renewal (SLR) request from Dominion Energy, the owners of V.C. Summer...
The Department of Energy reported on March 30 that the Savannah River Site’s H Canyon facility recently initiated actions to recycle a small amount of used high-enriched uranium (HEU). SRS...
A new animated video from the Department of Energy's Office of Environmental Management (EM) shows how cleanup contractor CH2M HILL BWXT West Valley (CHBWV) will take down the main plant...
Our Friday Matinee for today is the latest of the excellent Vogtle Timeline videos produced by Georgia Power to document the construction progress of Vogtle Units 3 and 4. The series stands...
This week's Friday Matinee features an update on the construction progress at Plant Vogtle's Units 3 and 4, the new AP1000 units being built in Georgia. This is the First Quarter 2016 update...
This week's ANS Nuclear Cafe Friday Matinee features an update from South Carolina Electric & Gas on "A Year of Progress for V. C. Summer Units 2 and 3." These two AP1000 units are being...
This week's feature is a half hour documentary on the history of the National Reactor Testing Station, or NRTS (now part of Idaho National Laboratory) which has seen 52 different and largely...
The versatile, powerful and unique ATR (Advanced Test Reactor) at Idaho National Laboratory is featured in this video describing it, the history of materials testing reactors that led up to...
This new video from AREVA takes a fascinating look at the "brain and nervous system" for controlling a nuclear power plant: the plant's Instrumentation and Control (I&C) system....